Perimeter Guarding Case study

In late 2017, based on ISO 13857, Amazon decided that it needed to change the specifications for its perimeter guarding (fencing) which segregates and protects employees from the robotic inventory systems. Amazon  required  that any  vendor that wished  to  supply perimeter guarding going forward create a design that was fully compliant with Amazon requirements and …

NPSG Global Case Study: “Fences”

Our client, a Major e-Retail Fulfillment Center Startup Manager, discusses our response to a critical situation   “The first day I met Eric and NPSG, I was working on a project involving robotics implementation in California. One of my counterpart PMs was working on a similar project in Texas. I was supposed to go first in California, …

NPSG Global Case Study “Pods”

A conversation with our Major e-Retail Fulfillment Center Startup Manager   “I was tasked with converting some buildings at three different locations from static shelving to a robotics system. All these static shelves that could have a robot pick them up and move them around, we set them up in a static configuration. When the time came …